Bahasa Inggris Chapter 7 "A Guide to the project management body of knowledge"
Chapter 7
Project Cost Management
Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7-1 provides an overview of the following major processes:
7.1. Resource Planning—determining what resources (people, equipment, mate- rials) and what quantities of each should be used to perform project activities.
7.2 . Cost Estimating—developing an approximation (estimate) of the costs of the resources needed to complete project activities.
7.3. Cost Budgeting—allocating the overall cost estimate to individual work activities.
7.4Cost Control—controlling changes to the project budget. These processes interact with each other and with the processes in the other knowledge areas as well. Each process may involve effort from one or more indi- viduals or groups of individuals, based on the needs of the project. Each process generally occurs at least once in every project phase.
Although the processes are presented here as discrete elements with well- defined interfaces, in practice they may overlap and interact in ways not detailed here. Process interactions are discussed in detail in Chapter 3.
Project cost management is primarily concerned with the cost of the resources needed to complete project activities. However, project cost management should also consider the effect of project decisions on the cost of using the project’s product. For example, limiting the number of design reviews may reduce the cost of the project at the expense of an increase in the customer’s operating costs. This broader view of project cost management is often called life-cycle costing. Life- cycle costing together with Value Engineering techniques are used to reduce cost and time, improve quality and performance, and optimize the decision-making.
In many application areas, predicting and analyzing the prospective financial performance of the project’s product is done outside the project. In others (e.g., capital facilities projects), project cost management also includes this work. When such predictions and analyses are included, project cost management will include additional processes and numerous general management techniques such as return on investment, discounted cash flow, payback analysis, and others.
Project cost management should consider the information needs of the project stakeholders—different stakeholders may measure project costs in different ways and at different times. For example, the cost of a procurement item may be mea- sured when committed, ordered, delivered, incurred, or recorded for accounting
purposes.
When project costs
are used as a component of a reward and
recognition system (discussed in Section 9.3.2.3), controllable and uncontrollable costs should be estimated and
budgeted separately
to ensure that
rewards reflect actual performance.
On some projects, especially smaller ones, resource planning, cost estimating, and cost
budgeting are so tightly
linked
that
they are viewed
as a single process
(e.g., they
may be performed by
a single individual over a relatively short
period of time).
They are presented here as distinct
processes because the tools and techniques for each are different. The ability to influence cost is greatest at the early stages of the project, and this is why early scope definition is critical, as well as thorough requirements identification and
execution of a sound plan.
7.1 RESOURCE
PLANNING
Resource planning involves determining what physical resources (people, equip- ment, materials) and what
quantities of each should be used and when
they would be needed to perform project
activities. It must be closely coordinated with
cost estimating (described in
Section 7.2). For example:
■ A construction project team will need to be familiar
with local building codes.
Such knowledge is often readily
available from local sellers. However, if the local labor pool
lacks
experience with unusual or specialized construction techniques, the additional cost for a consultant might be the most
effective way to secure
knowledge of the local building codes.
■ An automotive design
team should be familiar
with the latest in automated
assembly techniques. The requisite knowledge
might be obtained by hiring a consultant, by sending a designer to a seminar on robotics, or by including someone from manufacturing as
a member of the team.
7.1.1 Inputs
to Resource Planning
.1 Work breakdown structure. The work breakdown structure (WBS, described in Section
5.3.3.1) identifies
the project
deliverables and processes that will need resources, and
thus
is the primary input to resource planning. Any relevant out- puts from other
planning processes
should be provided through the WBS to ensure proper control.
.2 Historical
information. Historical information regarding what types of resources
were required
for similar work on previous projects should be used if available.
3 Scope statement. The scope statement (described in Section
5.2.3.1) contains the project justification and the project objectives, both of which should be
con- sidered explicitly during resource planning.
.4 Resource
pool description. Knowledge of what resources (people, equipment, mate- rial) are potentially available is necessary for resource planning. The amount of detail and the level of specificity
of the resource pool
description will vary.
For example, during the early phases
of an engineering design
project, the pool may include
“junior
and senior engineers” in large numbers. During later phases
of the same project, however, the pool may be limited to those individuals who are knowl- edgeable about
the project as a result of having worked
on the earlier phases.
.5 Organizational policies. The policies of the performing organization regarding
staffing and the rental
or purchase of supplies and equipment must be considered during resource
planning.
.6 Activity duration estimates. Time durations (described in
Section 6.3.3.1).
7.1.2 Tools and Techniques for Resource Planning
.1 Expert judgment. Expert judgment will often be required to assess the inputs
to this process. Such expertise may be provided by any group or individual with spe- cialized knowledge or training,
and is available from many sources including:
■ Other units within the performing organization.
■ Consultants.
■ Professional
and technical associations.
■ Industry groups.
.2 Alternatives identification. Alternatives identification is discussed in Section
5.2.2.3.
.3 Project management software.
Project management software
has the capability to help organize resource
pools. Depending upon the sophistication of the software, resource availabilities and rates can be defined, as well as resource calendars.
7.1.3 Outputs
from Resource Planning
.1 Resource
requirements. The output of the resource planning process is a description of what types of resources are required and in what quantities for each element at the lowest level of the WBS. Resource requirements for higher
levels within the WBS can be calculated based on the lower-level values.
These resources will be obtained either
through staff acquisition (described in Section 9.2) or procurement (described in Chapter 12).
7.2 COST ESTIMATING
Cost estimating involves developing an approximation (estimate) of the costs of the resources needed to complete project activities. In approximating cost, the estimator considers the causes
of variation of the final estimate for purposes of better managing the project.
When a project is performed under
contract, care should
be taken to distinguish cost
estimating from pricing.
Cost estimating involves developing an assessment of the likely quantitative result—how much will it cost the performing organization to provide the product or
service involved? Pricing is a business decision—how
much will the performing organization charge for the product or service—that uses
the cost estimate as but one consideration of many.
Cost estimating includes identifying and considering various costing alterna- tives. For example, in most application areas,
additional work during a design phase is widely
held to have the potential for reducing the cost of the production phase. The cost-estimating process
must
consider whether the cost of the addi- tional design work will be offset
by the expected savings.
I7.2.1 Inputs
to Cost Estimating
.1 Work breakdown structure. The WBS is described in Section 5.3.3.1. It is used to orga- nize the cost estimates and to ensure that all identified work has been estimated.
.2 Resource
requirements. Resource requirements are described in Section 7.1.3.1.
.3 Resource
rates. The individual or group preparing the estimates must know the unit rates (e.g.,
staff cost per hour,
bulk material cost per cubic yard) for each resource to calculate project
costs. If actual rates are not known, the rates them-
selves may have to be estimated.
.4 Activity duration estimates. Activity duration estimates
(described in Section 6.3.3.1) will affect cost
estimates on any project
where the
project budget includes an allowance for the cost of financing (i.e., interest charges).
.5 Estimating publications. Commercially available data on cost estimating.
.6 Historical information. Information on the cost of many categories of resources is often available from one or more of the following sources:
■ Project files—one
or more of the organizations involved
in the project may
maintain records of previous project results that are detailed enough to aid in developing cost estimates. In some application areas,
individual team mem- bers may maintain such records.
■ Commercial cost-estimating databases—historical information is often avail-
able commercially.
■ Project team knowledge—the individual
members of the project
team may remember previous
actuals or estimates. While such recollections may be useful, they
are generally far less reliable than
documented results.
.7 Chart of accounts. A chart of accounts describes
the coding structure used by the performing organization to report financial information in its general ledger. Project cost estimates must be assigned to the correct
accounting category.
.8 Risks. The project team considers information on risks (see
Section 11.2.3.1) when producing cost estimates, since risks (either threats or opportunities) can have a significant impact on cost. The project
team considers the extent to which the effect of risk is included in the cost estimates for each activity.
7.2.2 Tools and Techniques for Cost Estimating
.1 Analogous
estimating. Analogous estimating,
also called top-down estimating, means using the actual
cost of a previous, similar
project as the basis for esti- mating the
cost of the current project. It is frequently used
to estimate total project costs when there is a limited amount of detailed information about
the project (e.g.,
in the early phases). Analogous
estimating is a form of expert judg-
ment (described in
Section 7.1.2.1).
Analogous estimating
is generally less costly than other techniques, but it is also generally less accurate.
It is most reliable when a) the previous projects are
similar in fact and
not just
in appearance, and b) the individuals or groups preparing the estimates have the needed expertise.
.2 Parametric modeling. Parametric modeling
involves using project
characteristics (parameters) in a mathematical model to predict
project costs. Models may be simple (residential home
construction will cost a certain amount per square foot of living space) or complex (one model of software development costs uses thir- teen
separate adjustment factors, each of which has five to seven
points
on it).
Both the cost and accuracy
of parametric models
vary widely. They are most likely to be reliable
when a) the historical information used to develop
the model was accurate, b)
the parameters used in the model
are readily quantifiable, and
c) the model
is scalable (i.e., it works as well for a very large project as for a very small one).
.3 Bottom-up
estimating. This technique involves
estimating the cost of individual
activities or work packages, then summarizing or rolling
up the individual esti- mates to get a project total.
The cost and accuracy of
bottom-up estimating is driven by the size and com- plexity
of the individual activity or work package: smaller
activities increase both cost and accuracy
of the estimating process. The project
management team must weigh the additional accuracy against
the additional cost.
.4 Computerized tools. Computerized tools, such as project management software spreadsheets and simulation/statistical tools,
are widely used to assist with
cost estimating. Such products can simplify the use of the tools described earlier
and thereby facilitate rapid consideration of many costing alternatives.
.5 Other cost estimating methods.
For example, vendor bid analysis.
7.2.3 Outputs
from Cost Estimating
.1 Cost estimates. Cost estimates are quantitative assessments of the likely
costs of the resources required to complete project
activities. They may be presented in summary or in detail.
Costs must be estimated for all resources that will be charged to the project. This includes, but is not limited to, labor, materials, supplies, and special cate- gories such
as an inflation allowance
or cost reserve.
Cost estimates are generally expressed
in units
of currency (dollars, euros, yen, etc.) to facilitate comparisons
both within and across projects. In some cases, the estimator may use units of measure to estimate cost, such as staff hours
or staff days, along with their cost
estimates to facilitate appropriate management control. Cost estimating generally includes
considering appropriate risk response planning, such as contingency plans.
Cost estimates may benefit from being refined
during the course of the project to reflect
the additional detail available. In some application areas,
there are guidelines for when such
refinements should be made and what degree of accu- racy is expected. For example, The Association for the Advancement of Cost Engi- neering (AACE) International has identified a progression of
five types
of estimates of construction costs during engineering: order
of magnitude, concep- tual, preliminary, definitive, and control.
.2 Supporting
detail. Supporting detail for the cost estimates should include:
■ A description of the scope of work estimated. This is often provided by a ref- erence to
the WBS.
■ Documentation
of the basis for the estimate;
i.e., how it was developed.
■ Documentation
of any assumptions made.
■ An indication of the range of possible results; for example, $10,000
± $1,000 to indicate that the item is expected to
cost between $9,000 and $11,000.
The
amount and type of additional details vary by application area. Retaining
even rough notes may prove valuable by providing a
better understanding of how the estimate was developed.
.3 Cost management plan.
The cost management plan describes how cost variances will be managed (e.g.,
different responses
to major
problems than to minor ones). A cost management plan may be formal
or informal, highly detailed or broadly framed, based on the needs of the project stakeholders. It
is a subsidiary element of
the project plan (discussed in Section 4.1.3.1).
7.3 COST BUDGETING
Cost budgeting involves
allocating the overall cost estimates to individual activi- ties or work packages to establish a cost baseline for measuring project perfor- mance. Reality may dictate that
estimates are done
after budgetary approval is provided, but estimates should
be done prior to budget request wherever possible.
7.3.1 Inputs
to Cost Budgeting
.1 Cost estimates. Cost estimates are described in
Section 7.2.3.1.
.2 Work breakdown structure.
The WBS (described in Section 5.3.3.1) identifies
the project elements to
which costs
will be allocated.
.3 Project schedule. The project schedule (described in Section
6.4.3.1) includes planned start and expected finish dates for the project components to which costs will be allocated. This information is needed to assign costs to the time period when the cost will be incurred..4 Risk management plan. The risk management plan is discussed in Section 11.1.3.
In addition to this, the risk management plan often includes cost contingency, which
can be determined on the basis of the expected accuracy
of the estimate.
7.3.2 Tools and Techniques for Cost Budgeting
.1 Cost budgeting tools and techniques. The tools and techniques described
in Sec- tion 7.2.2 for developing project
cost estimates are used to develop budgets for activities or work packages as
well.
7.3.3 Outputs
from Cost Budgeting
.1 Cost baseline. The cost baseline is a time-phased budget that
will be used to measure and monitor cost performance on the project. It is developed by sum- ming estimated costs by period
and is usually displayed in the form of an S-curve, as illustrated
in Figure 7-2.
Many projects, especially larger ones,
may have multiple cost baselines to measure different aspects of cost performance. For example, a
spending plan or cash-flow forecast is a cost baseline for measuring disbursements.
7.4 COST CONTROL
Cost control is concerned with a) influencing the factors
that create
changes to the cost baseline to ensure that changes are agreed
upon, b) determining that the cost baseline has changed, and c) managing the actual
changes when and as they occur. Cost
control includes:
■ Monitoring cost performance to detect and
understand variances from plan.
■ Ensuring that all appropriate changes are
recorded accurately in the cost baseline.
■ Preventing incorrect, inappropriate,
or unauthorized changes from being
included in the cost baseline.
■ Informing appropriate stakeholders of authorized changes.
■ Acting to bring expected costs within acceptable limits.
Cost control includes
searching out the “whys” of both positive and negative variances. It must
be thoroughly integrated
with the other control
processes (scope
change control, schedule
control, quality control, and others, as discussed in Section
4.3). For example, inappropriate responses to cost variances can cause quality or schedule problems, or produce an unacceptable level of risk later in the project.
7.4.1 Inputs
to Cost Control
.1 Cost baseline. The cost baseline is
described in Section 7.3.3.1.
.2 Performance reports. Performance reports (discussed in Section 10.3.3.1) provide information on project scope and cost performance, such as which budgets have been
met and
which
have not.
Performance reports may also alert the project team to issues that
may cause problems in the future.
.3 Change requests. Change requests may occur in many forms—oral or written, direct or indirect, externally or internally initiated, and legally
mandated or optional. Changes may require increasing
the budget or may allow decreasing it.
.4 Cost management plan.
The cost management plan is described in Section
7.2.3.3.
7.4.2 Tools and Techniques for Cost Control
.1 Cost change control system. A cost change
control system defines
the procedures by which the
cost baseline may be changed.
It includes the paperwork, tracking systems, and approval levels necessary for authorizing changes.
The cost change control system should
be integrated with the integrated change control
system, discussed in Section 4.3.
.2 Performance measurement. Performance measurement techniques, described in Section 10.3.2, help to assess the magnitude of any variations that do occur. Earned Value Management (EVM), described in Sections 7.4.2.3
and 10.3.2.4, is especially useful for cost control. An important part of cost control is to determine what is causing the variance and to decide
if the variance requires corrective
action.
.3 Earned value management (EVM).
All EVM Control Account
Plans (CAPs) must continuously measure project
performance by relating three independent vari- ables: 1) The Planned Value,
the physical
work scheduled to be performed, including the estimated value of this work (previously called the Budgeted Costs
for Work Scheduled [BCWS]),
as compared against the 2) The Earned Value, physical work
actually accomplished, including the estimated value of this work (previously called the
Budgeted Costs for Work Performed [BCWP]),
and
to the
3) Actual Costs incurred
to accomplish the Earned Value. The relationship of 2) Earned Value less 1) Planned Value constitutes the Schedule Variance
(SV). The relationship of 2) Earned Value less 3) Actual Costs constitutes the Cost Variance (CV) for the project. See also Section 10.3.2.4.
.4 Additional planning. Few projects run exactly according to plan. Prospective changes may require new or revised cost estimates or analysis
of alternative approaches.
.5 Computerized tools. Computerized tools, such as project management software and spreadsheets, are often used to track
planned costs versus actual costs, and to forecast the
effects of cost changes.
7.4.3 Outputs
from Cost Control
.1 Revised cost estimates. Revised cost estimates are modifications to the
cost information used
to manage the project. Appropriate stakeholders must be noti- fied as needed. Revised cost estimates may or may not require adjustments
to other aspects of
the project plan.
.2 Budget updates. Budget updates are a special
category of revised cost estimates.
Budget updates are changes to an approved cost baseline. These numbers are gen- erally revised
only in response to scope changes. In some cases, cost variances may be so severe that
rebaselining is needed to provide
a realistic
measure of performance.
.3 Corrective action. Corrective action is anything done to bring
expected future project performance in
line with the project plan.
.4 Estimate
at completion. An Estimate at Completion (EAC) is a forecast
of most likely total project costs based
on project performance and risk quantification, described in Section 11.4.3.
The most common forecasting techniques are some
variation of:
■ EAC = Actuals to date
plus a new estimate for
all
remaining work. This
approach is most often used when past performance shows that
the original estimating assumptions were fundamentally flawed,
or that they are no longer relevant to
a change in conditions. Formula: EAC = AC + ETC.
■ EAC = Actuals to date plus remaining budget (BAC – EV). This approach is
most often used when
current variances
are seen as atypical
and the project management team expectations are that similar
variances will not occur in the future. Formula:
EAC = AC + BAC –
EV.
■ EAC = Actuals
to date plus the remaining project
budget (BAC – EV) modified
by a performance factor, often the
cumulative cost performance
index (CPI).
This approach is most often used when current variances are seen as typical of future variances.
Formula: EAC = (AC + (BAC – EV)/CPI)—this CPI is the cumulative CPI.
Each of these
approaches may be the correct approach for any given project and will provide the project management team with
a signal if the EAC forecasts
go beyond acceptable tolerances.
.5 Project closeout. Processes and procedures should be developed for the closing or canceling of projects. For example, the Statement of Position (SOP 98-1 issued by the American Institute of
Certified Public Accountants—AICPA) requires
that all the costs for a failed information technology project
be written off in the quarter that the project is canceled.
.6 Lessons
learned. The causes of variances, the reasoning behind the corrective action chosen, and other
types
of lessons learned from cost control should
be documented so that they
become part
of the historical database
for both
this
project and other projects
of the performing organization (see Section 4.3.3.3).
Komentar
Posting Komentar